First Quantum Minerals Provides Progress Report on Kevitsa Nickel-Copper-PGE Project, Finland PDF Print E-mail
Thursday, 29 July 2010 20:09

First Quantum Minerals Ltd. (“First Quantum” or the “Company”, TSX Symbol “FM”, LSE Symbol “FQM”) provide a progress report on the Kevitsa nickel-copper-PGE project in Finland. The project was approved for development by the Company’s Board of Directors in November 2009 and is expected to begin commercial production in mid 2012.

Highlights

  • BNP Paribas and Standard Bank of South Africa jointly mandated to arrange a debt facility
  • Government support agreed for several infrastructure projects
  • On-site construction activity commenced with approximately 75 construction personnel currently on site
  • Ongoing drill program returns further positive results

Financing


BNP Paribas and Standard Bank of South Africa have been mandated as the lead arrangers for a debt facility of $250 million together with a €17 million stand-by letter of credit facility. Facility term is up to 7 years including 5 years repayment commencing September 30, 2012. The facility is expected to be available for first drawdown by no later than August 31, 2010.

Government Support


The excellent cooperation with the local, regional and Government authorities in Finland continues. An agreement has been reached with the Government to reimburse the Company for the cost of constructing the access road to the mine site. Construction of the road began in 2008 and is expected to be completed by the end of July, 2010. The Government has also committed to financially contribute to other infrastructure projects such as power and water services.

Engineering, Procurement and Construction


Basic engineering is nearing completion with Fluor in Australia, and detailed engineering design with Poyry, Finland is well underway. Essentially all long-lead equipment orders have been placed, with deliveries programmed to suit the construction schedule.

Major construction contracts have been awarded to Finnish contractors as follows:

  • Access road and bridge – Veljekset Karjalainen Oy (nearing completion)
  • Plant site earthworks and concrete works – Lemminkainen Oy (commenced)
  • Structural steelwork fabrication and erection – Naaraharju Oy
  • 110 kV power line – Empower Oy
  • Plant site HV switchyard – Vaasa Engineering Oy

Currently there are approximately 75 construction personnel on site and this will increase as additional construction works contracts are awarded. The plant site earthworks commenced in early June and are currently in progress in many areas.

The first structural concrete pours for the mill building foundations occurred on July 13, 2010. Steelwork details have been released to the fabrication contractor and steelwork erection is expected to commence in September, 2010.


Major equipment supplier, Outotec, is maintaining scheduled progress for the manufacture of the grinding mills, flotation cells, thickeners and concentrate filters.

The main access road to the site is in the process of being asphalted and the road sealing work is expected to be completed shortly.

Drill Program


The most recent mineral resource and mineral reserve estimates for Kevitsa were published on November 30, 2009. The drilling program has since continued to upgrade a portion of the inferred resource to indicated and measured and to identify the borders of the resource both laterally and along strike.

A summary of the program to date is as follows:

  • Over 15,000 metres of core drilling in 46 holes have been completed since November 2009.
  • Results have outlined a significant extension of mineralization to the south of the existing resource at relatively shallow depths.
  • Much of the mineralization lies either within or immediately adjacent to the current pit profile and is therefore expected to enhance the mineral reserve without compromising the anticipated strip ratio.
  • A new mineral resource model and reserve optimization is currently in progress and is expected to be finalized before year end 2010.
  • Several holes have been extended below the current open pit resource and demonstrate mineralization continuing at depths of over 900 metres encouraging the examination of potential options for bulk extraction from underground.
  • Drilling emphasis has now moved on to exploration for massive sulphide lenses on the northern and eastern contacts of the Kevitsa intrusion where recent geophysical surveys have defined several encouraging targets.

 

About the Kevitsa Nickel-Copper-PGE Project


The Kevitsa project is located approximately 142 kilometres north-northeast of Rovaniemi, the capital of Finnish Lapland. Measured and indicated resources, as at November, 2009, are estimated at 165 million tonnes grading 0.30% nickel; 0.27 nickel sulphide; 0.42% copper; using a nickel cut-off grade of 0.1%.The project has all material mining permits and was granted development approval by the Company’s Board of Directors in November 2009.

The capital cost estimate, of $400 million, is based on the mining, processing and infrastructure requirements to treat five million tonnes per annum but also taking into account the possibility of further expansions should conditions allow. Kevitsa is expected to begin commercial production in mid 2012. The estimated mine life is over 20 years and the life-of-mine C1 cash operating cost is estimated at approximately $2.50 per pound nickel, net of by-product credits.

The open pit mine is planned to employ large-scale electrically-powered mining equipment to deliver ore to the primary gyratory crusher. After crushing the ore will be autogenously milled prior to the two-staged flotation process. Two concentrates will be produced – a copper/gold concentrate and a nickel concentrate that will contain the majority of the platinum group elements (“PGE’s”).

Off-take arrangements for the separate treatment of both concentrates will target international as well as local smelters.

Bookmark this page!
Ask.com del.icio.us Digg.com Facebook folkd.com Google Hao Hao Report Netscape StumbleUpon Technorati Webnews Mister Wong Yahoo

Last Updated on Thursday, 29 July 2010 22:04
 



Stay informed, receive our monthly newsletter!

We have 208 guests online

http://www.emp-antriebstechnik.de
Mining technology - Made in Germany - leading world-wide
LHD-Loader PFL - payloads 1,5 t - 5,5 t  - optimum solution mining tunnelling
hoisting technology and mine-shaft infrastructure Siemag Tecberg http://www.siemag-tecberg.com
Cool Air and a Fresh Breeze in Mining and Tunnelling - We care for You - Herco-gmbh.com
Universa 50 versatile carrier vehicle payloads up to 15 tons
HSE Industrial Safety Employment Protection Fire S-I-B SIB sicher im betrieb de prevention
http://www.cft-gmbh.de
Spezialmaschinen und Komponenten fuer Anwendungen im Berg- und Tunnelbau
Self-propelled working platform and standard telescopic-swivel loader combined in one machine
Cool Air and a Fresh Breeze in Mining and Tunnelling - We care for You - Tunnel-Ventilation.de
http://www.indurad.com
Tools for drilling and rockbolting Drill bits Drill rods Drill shanks Drag bits Sleeves and adapters
PC-Soft GmbH is positioning itself on the market as one of the first and leading providers of integrated software
Halbach and Braun Industrieanlagen GmbH Germany
VGE Verlag GmbH - Montebruchstraße 2, D-45219 Essen - Germany - Tel. + 49 (0) 20 54 / 924-0 - Fax + 49 (0) 20 54 / 924-109 - E-Mail: info@vge.de
Layout / Technische Umsetzung: www.denkbetrieb.de - Ihre Full Service Werbeagentur im Ruhrgebiet koordination und abwicklung: moduscom unternehmenkommunikation manfred könig